The variation compare only the first initial planning with the current
planning.
How to get the variation between the second initial planning and the current
planning ?
In fact, what is the use of the 11 initial planning if we can't compare them
each others ?
Cette action est irreversible, confirmez la suppression du commentaire ?
Signaler le commentaire
Veuillez sélectionner un problème
Nudité
Violence
Harcèlement
Fraude
Vente illégale
Discours haineux
Terrorisme
Autre
Didier Maignan | EPM expert - CLC
Hi ShadowfilwithNoName,
You can use formulas to compare dates, in working days. You just need to create customed fields, which makkes the power of EPM tool.
To save 11 initial planning ( A B C D ...) I suggest to create a button in the tool bar to do so, and to show the good view, with the good table inside. Hopes this helps.
The variation compare only the first initial planning with the current planning. How to get the variation between the second initial planning and the current planning ?
In fact, what is the use of the 11 initial planning if we can't compare them each others ?
What strategy to save the 11 initial planning ?
Thank you for your help.
Hi ShadowfilwithNoName,
You can use formulas to compare dates, in working days. You just need to
create customed fields, which makkes the power of EPM tool.
To save 11 initial planning ( A B C D ...) I suggest to create a button in
the tool bar to do so, and to show the good view, with the good table
inside.
Hopes this helps.
"ShadowFil" <ShadowFil@discussions.microsoft.com> a écrit dans le message de
news: AB50CB46-BAA8-438B-A8FC-0DAE8425365C@microsoft.com...
Hello,
The variation compare only the first initial planning with the current
planning.
How to get the variation between the second initial planning and the
current
planning ?
In fact, what is the use of the 11 initial planning if we can't compare
them
each others ?
You can use formulas to compare dates, in working days. You just need to create customed fields, which makkes the power of EPM tool.
To save 11 initial planning ( A B C D ...) I suggest to create a button in the tool bar to do so, and to show the good view, with the good table inside. Hopes this helps.
The variation compare only the first initial planning with the current planning. How to get the variation between the second initial planning and the current planning ?
In fact, what is the use of the 11 initial planning if we can't compare them each others ?